Port Klang is ideally placed to capitalise on the domestic and international markets. The three container terminals now handle a total capacity of 3.6 million TEUs per annum, and is expected to handle 8.4 million TEUs by the year 2010.
 
Northport
The Northport CT1 operates 4 berths at its terminal:
  Berth No. 8
This container berth caters to vessels of up to 40,000 tonnes displacement.

Berth No. 9, 10, 11
Can accommodate ships of up to 60,000 tonnes displacement.

 
Berthing Facilities
Berth No. Length (m) Depth alongside Max vessel size (displacement tonnes)
8
9
10
11
213
320
320
226
10.5
13.2
13.2
13.2
40,000
60,000
60,000
60,000
 
   
The Northport CT2 has 5 berths of 1.1 km for ships of up to 80,000 tonnes displacement.
 
Berthing Facilities
Berth No. Length (m) Depth alongside Max vessel size (displacement tonnes)
17
18
19
20
21
213
213
213
213
213
13
13
13
13
13
80,000
80,000
80,000
80,000
80,000
 
   
The Northport CT3 operates 3 berths at its terminal and can accommodate ships of up to 120,000 tonnes displacement.
 
Berthing Facilities
Berth No. Length (m) Depth alongside Max vessel size (displacement tonnes)
12
13
14
178
178
178
15
15
15
120,000
120,000
120,000
 
   
   
Westports
 

Berthing Facilities

Berth No.
Length (m)
Depth alongside
Max vessel size (displacement tonnes)

B07

300

15

80,000

B08

300

15

80,000

B09

300

15

115,000

B10

300

15

115,000

B11 300 15 115,000
B12 300 15 115,000
 
  The 3 terminals have sophisticated back-up facilities such as post-Panamax quay cranes, RTGs and straddle carries to handle up to 1.05 million TEUs.
   
  Last Updated : June 27, 2007